Phase 0 entails reclaiming 50 hectares of land starting from the northwest corner of Main Island and is expected to be completed in mid-2011.
The illustration to the right shows how reclamation work will progress on the first 15 hectares of Phase 0 through July 2010.
Construction on finished land will begin in the first quarter of 2010 and continue progressively as land is reclaimed.